Deep Green Data Center – Conditional Rezoning (Z-2-2025)
Lansing
Description
Conditional rezoning from DT-3 Urban Core to IND-1 Industrial for a 24-megawatt heat-reuse data center; condition limits the site to a data center use. Public hearing set for February 9.
Impact summary
All five public commenters opposed it, citing fuel-cell emissions, a Planning Commission member's reversed vote, and lost downtown potential.
Applicant
- Name
- Deep Green Technologies USA LLC
- Address
- 220 S. Larch St. and 3 adjoining parcels on E. Kalamazoo St. and S. Cedar St., Lansing, MI
At a glance
- Hearings
- 3
- Public comments
- 65
- Total mentions
- 3
Recorded in the meeting · Committee of the Whole
Last discussed Mar 9, 2026.
Meeting timeline (3)
City Council - Mar 9, 2026
Rezoning from Urban Core to Industrial for the Deep Green data center, with conditions limiting use to data center operations and keeping DT-3 design standards; hearing April 6.
Committee of the Whole - Jan 12, 2026
Conditional rezoning from DT-3 Urban Core to IND-1 Industrial for a 24-megawatt heat-reuse data center; condition limits the site to a data center use. Public hearing set for February 9.
City Council - Jan 12, 2026
Four parcels would be rezoned to industrial with the condition that the only allowed use is a data center and its supporting facilities. First reading done; February 9 hearing set.
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Lansing
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.