Summary
The Country Club of Lansing easement resolution was tabled again while the city finalizes language — the easement would run behind two homes instead of through the street. Construction isn't expected until 2027.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 24, 2026.
Impact analysis
Costs aren't stated, but the new infrastructure is expected to last up to 80 years.
The drainage project and the Country Club of Lansing once easements are finalized.
Two homeowners whose backyards would host the easement may want to weigh in.
Mentions & discussions (2)
Committee on City Operations - Sep 24, 2026
The Country Club of Lansing easement resolution was tabled again while the city finalizes language — the easement would run behind two homes instead of through the street. Construction isn't expected until 2027.
Planning Commission - Aug 5, 2026
The city needs permanent easements to rebuild a 78-inch culvert and replace a sewer line along Moores River Drive, including land partly owned by the Country Club of Lansing, which has agreed. Tree removal starts this winter; construction is slated for July 2027.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Lansing
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.